Text
1. The plaintiff, the defendant corporation, the re-construction of the defendant corporation, the 1,870,000 won and the 14,000,000 won and each of them.
Reasons
1. Basic facts
A. On June 15, 2014, the Plaintiff entered into a contract for construction work with Defendant Reconstruction Co., Ltd. (hereinafter “Reconstruction”) at Defendant 1’s order and with respect to the construction work for factories B located in Young-si (hereinafter “instant construction”), 524,00,000 won on June 15, 2014; 4 months from the date of commencement of construction; and 1/1000 on August 29, 2014; and 0.0,00 won on December 12, 2014; 200,000 won on December 14, 2014, the Plaintiff transferred to Defendant Reconstruction Co., Ltd. (hereinafter “Reconstruction”) at KRW 10,000,000,000 to the Plaintiff. The Plaintiff paid the construction work price to Defendant Reconstruction at KRW 10,000,000,000 on December 12, 2014.
Defendant Re-construction failed to complete the instant construction work by February 28, 2015, which was the deadline for construction extended as above.
[Reasons for Recognition] A without dispute, Gap evidence 1 to 4, Gap evidence 12-1 to 8, Gap evidence 38-1, 2, Gap evidence 39, 40, 43, and 46, and witness C.