logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원평택지원 2017.12.28 2016가합655
공사대금 등
Text

1. The Defendant (Counterclaim Plaintiff)

A. The Plaintiff (Counterclaim Defendant) Company A amounting to KRW 90,000,000 and that on July 6, 2016.

Reasons

1. Basic facts

A. On June 24, 2015, the Defendant awarded a contract for a new construction work (hereinafter “instant construction work”) to the Plaintiff for a construction cost of KRW 310,00,000 for a building [3 floors of detached houses (154.47 square meters of a floor, 65.82 square meters of a floor, 154.47 square meters of a floor, 65.82 square meters of a floor, 193.74 square meters of a second floor, 149.52 square meters of a floor; hereinafter “instant building”) located in Ansan-si D (E) (E) (hereinafter “instant construction”).

(hereinafter “The instant construction contract”). At the time of the instant construction contract, the Defendant and the Plaintiff did not separately set the construction period, and in relation to the payment of the construction cost, the Defendant agreed to pay the Plaintiff A the balance after completion of the contract, including KRW 100,000,000 (value-added tax), August 10, 2015.

B. According to the instant construction contract, the Defendant paid the Plaintiff KRW 128,000,000,000 on June 24, 2015, and KRW 10,000 on August 11, 2015, and KRW 128,00,000 on September 21, 2015.

2. Total amount of the construction cost settlement method: 150,000,000 won for the payment method of 10,000 won for November 10, 16, 10,000 won for 10,000 won for 10,000 won for 16 November 23, 191, and the remainder of 20,000 won for 30,000 won for 10,000 won for 30,000 won for 10,000 won for 10

3. 1) The scope of the project shall be limited to a room for outside timber construction; 1) the project on the roof, the project on the roof, the project on the roof, the project on the roof, the project on the roof, or the project on the stude; 2) the rooftop shall be limited to a room;

3) The installation of telecommunication, fire-fighting, and telecommunication (videophone) is excluded from the external testing on drawings.

5) The plaintiff A shall be fully responsible for the completion of the construction, except as otherwise expressly agreed. 6) All liabilities due to the completion of the construction, except as otherwise agreed.

Plaintiff

B shall complete all the construction works not covered by the above-mentioned Special Agreement until completion is completed.

C. On November 10, 2015, after the conclusion of the instant construction contract, the construction project was not implemented properly, Plaintiff A subcontracted part of the instant construction project to Plaintiff B. The specific details are as follows.

(hereinafter referred to as the “instant subcontract,” and this part of the construction performed by Plaintiff B is referred to as the “instant subcontract,” Plaintiff.

arrow