(영문) 광주지방법원 2016.03.24 2015가단55118
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 39,250,000 and the interest rate of KRW 15% per annum from November 18, 2015 to the date of full payment.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

(However, the “creditor” shall be deemed to be the “Plaintiff”, and the “debtor” shall be deemed to be the “Defendant”). 2. Judgment of deemed confession (Article 208(3)2 of the Civil Procedure Act)

3. That damages for delay exceeding the rate of 15% per annum from October 1, 2015 pursuant to the provisions on statutory interest rate under the main sentence of Article 3 (1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (Presidential Decree No. 26553) are not recognized (see Article 2 (2) of the Addenda to the foregoing Regulations).