(영문) 서울중앙지방법원 2015.02.06 2014가단167390
대여금
Text

1. The Defendant’s KRW 51,00,000 as well as the Plaintiff’s annual rate from October 17, 2014 to February 6, 2015.

Reasons

1. Indication of claims: To be as shown in attached Form of claims;

(However, a claim for a loan of KRW 19 million as of December 11, 2013 was reduced to KRW 18 million, and a claim for a loan of KRW 3 million as of December 16, 2013 was withdrawn). 2. Decision by service by public notice (Article 208(3)3 of the Civil Procedure Act)

3. The Plaintiff’s dismissal portion also claims the amount of money calculated at the rate of 5% per annum for the period from the day following each lease to the day of service of the complaint of this case. However, there is no evidence to prove that there was an interest agreement with the Defendant, and there is no evidence to prove that there was an agreement between the Defendant, and thus, damages for delay can be claimed only from

arrow