(영문) 부산지방법원 2018.08.24 2017구합23866
손실보상금
Text

1. The Defendant’s KRW 52,99,950 for the Plaintiff and 5% per annum from December 23, 2017 to August 24, 2018.

Reasons

The project approval and public announcement - B housing redevelopment project - The defendant (i.e., July 26, 2006) - the public announcement of 10 to 25 square meters: 30, 70, 30, 47, 50, 30, 47, 57, 20, 30, 47, 57, 20, 57, 20, 30, 57, 30, 57, 20, 57, 20, 30, 57, 30, 57, 206, 30, 57, 50, 207, 205, 30, 57, 206, 306, 57, 205, 97, 205, 206, 207, 306, 207, 207, 205,

As of October 30, 2017, the appraisal result of the appraiser Q Q, which belongs to the appraisal corporation company, selected by the court, is as follows, the compensation amount of KRW 1,393,55,200, which is appraised as the result of the combination of the land of this case with the I major 802 square meters as of October 30, 2017, and the compensation amount of KRW 1,186,356,200 (=798,728,728,200, KRW 228,457,200, KRW 110,483,400, KRW 487,687,60) is divided.

arrow