(영문) 인천지방법원 2017.04.19 2016가단42915
공사대금
Text
1. The Defendant shall pay to the Plaintiff KRW 41,00,000 and the interest rate of KRW 15% per annum from March 31, 2017 to the date of full payment.
Reasons
1. The Plaintiff’s goods and construction cost claim amounting to KRW 41,00,000 against the Defendant following the Plaintiff’s commission from June 2, 2015 to August 2, 2015 (Article 208(3)3 of the Civil Procedure Act).