(영문) 수원지방법원 2018.06.14 2017구합70930
개발부담금부과처분취소
Text

1. All of the plaintiffs' claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Details of the disposition;

A. On August 11, 2015, the Plaintiffs obtained permission from the Defendant to install facilities for storing and treating hazardous substances in the member-gu C, D, and E (a total of 3,133 square meters, hereinafter “instant land”) in Ansan-si, Ansan-si, the Plaintiffs owned by the Plaintiffs, and obtained approval for the use of the charging station newly established on April 28, 2017.

B. On July 11, 2017, the Defendant notified the Plaintiffs that the development charges for the instant land will be imposed KRW 307,502,470, and the Plaintiffs asserted that the development charges were calculated excessively, and filed a request for review before notifying the Defendant of the development charges.

C. On August 31, 2017, the Defendant imposed development charges of KRW 255,815,980 (hereinafter “instant disposition”) on the Plaintiffs by reducing part of the development charges for the instant land as follows.

Development gains - (1) - (2) development gains - (2) development gains - (2) development gains - 1,023,263,263,926 development charges x imposition rate (0.25), 25,815,980 (hereinafter referred to as "development gains - 1,025), 25,815,980 (hereinafter referred to as "10 won") at the time the land price as at the time of completion of the classification calculation - (2) 526,730,879,414 development gains -

D. Meanwhile, in order to calculate development charges on the instant land, the Defendant selected the unit F land in Ansan-si as a comparative standard site for the purpose of calculating the land price, and compared with the instant comparative standard site, compared with the instant land and the instant land, set the price allocation rate as indicated below, and calculated the instant land as KRW 84,000 per square meter as the instant comparative standard site.

In the case of a road adjacent to a low-water zone of land category of the specific use area, it refers to the land adjacent to the development restriction zone of this case, natural green-belt oil station site, commercial horizontal three-dimensional road, the width of which is at least 25 meters.