(영문) 창원지방법원 2015.02.10 2014가단11324
공사대금
Text

1. The defendant shall pay 26,851,000 won to the plaintiff and 20% per annum from April 30, 2014 to the day of full payment.

Reasons

Comprehensively taking account of the purport of each statement in Gap evidence Nos. 1 through 3, the plaintiff completed the above construction by entering into a subcontract with the defendant on July 201, 201 for the construction of the package after the underground water supply facilities near the current bathing beach site located at the time of macro-si, and the construction cost therefrom is KRW 17,010,000 (excluding value-added tax). On August 30, 2011, the plaintiff completed the above construction after entering into a subcontract for the breaking and packing of the construction site from the defendant in front of the Jhae Navy training center at the time of the Jhae Navy, and the construction cost therefrom is KRW 7,40,000 (excluding value-added tax).

Therefore, the Defendant is obligated to pay to the Plaintiff the construction cost of KRW 26,851,00 [=(17,010,000 + 7,400,000 + 110%) and the damages for delay calculated by the rate of 20% per annum from April 30, 2014 to the date of full payment, which is the day following the delivery date of the original copy of the instant payment order.

arrow