logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2016.01.27 2015나6750
양수금
Text

1. The defendant's appeal is dismissed.

2. The costs of appeal shall be borne by the Defendant.

Purport of claim and appeal

1..

Reasons

1. Facts of recognition;

A. The Plaintiff, who manufactured and processed the claim fire pipelines against D, entered into a contract for the supply of fire-fighting pipes with D Co., Ltd. (hereinafter “D”) which is engaged in the fire-fighting equipment business, etc. and supplied D with fire-fighting pipes equivalent to KRW 95,052,319 until July 31, 2013.

B. 1) C (the instant construction contract, etc.) was mutually modified at H on December 27, 2013.

hereinafter referred to as "project owner"

) The building of automobile sales facilities (hereinafter referred to as “instant building”) on the ground B of Yeongdeungpo-gu, Young-gu, G at the time of tolerance.

(2) Around June 20, 2012, the Defendant entered into a subcontract with G for electrical and fire-fighting installation works of the instant building at KRW 1.1 billion (including value-added tax) among the new construction works of the instant building.

3) On July 1, 2013, D is the fire-fighting facility works among the above electricity and fire-fighting facility works subcontracted by the Defendant between the Defendant and the Defendant (hereinafter “instant construction”).

(i) Contract price for construction with respect to construction: 462,00,000 won [50% of the contract price for construction (for example, giving up materials and personnel inputs in two installments) and the balance: Within one month after completion of construction (after payment by the original office): The period: From March 10, 2013 to July 31, 2013; the amount of construction price for delay x the number of delayed days x the number of delayed days x 0.1% (hereinafter “instant contract for construction”).

(C) After concluding the instant contract, the Plaintiff performed the instant construction by using the fire-fighting pipe, etc. supplied by the Plaintiff. (1) The Plaintiff did not receive KRW 85,052,319 out of the price of the fire-fighting pipe, etc. supplied by D as above. As such, on October 16, 2013, the Plaintiff entered into a contract for the assignment of claims (hereinafter “instant contract for the assignment of claims”) with the Plaintiff to transfer KRW 85,052,319 out of the instant contract price claim against D against the Defendant with D’s actual manager E.

At the time of this case, E shall be the same.

arrow