(영문) 서울중앙지방법원 2018.07.12 2017가단5128735
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 35,00,000 and the interest rate of KRW 15% per annum from June 16, 2018 to the day of complete payment.

Reasons

1. Facts of recognition;

A. The Plaintiff supplied 180,360,000 won and completed the construction work with respect to the office of the Defendant Company located in Gangnam-gu Seoul Building C (67th and 7th floor) from the Defendant.

B. However, the Plaintiff and the Defendant adjusted the construction cost to KRW 165 million on June 6, 2017, which was before the completion of construction works.

C. In addition, the Plaintiff, at the Defendant’s request, installed the first floor house, and paid the price of KRW 10 million on behalf of the Defendant.

[Grounds for recognition] Facts that the defendant does not clearly dispute, Gap evidence No. 1, and the purport of the whole pleadings

2. According to the above facts of recognition, the Defendant is obligated to pay to the Plaintiff the amount of KRW 25 million and the amount of KRW 10 million in total, and KRW 35 million in total, and damages for delay calculated at the rate of 15% per annum from June 16, 2018 to the date of full payment, which is the day following the day on which the second pleading statement on reduction of claim was delivered to the Defendant, as sought by the Plaintiff.

3. It is so decided as per Disposition because the plaintiff's claim is reasonable.