Text
1. The Defendant shall pay the Plaintiff KRW 26,00,000 and the interest rate of KRW 15% per annum from September 5, 2015 to the date of complete payment.
Reasons
The facts that the Plaintiff loaned KRW 3 million to the Defendant on February 21, 2013, KRW 6 million on February 27, 2013, KRW 3 million on February 28, 2013, KRW 9 million on February 28, 2013, KRW 4 million on the following day, and KRW 26 million on March 22, 2013 are deemed to have been led to the Defendant’s confession (Article 150(1) of the Civil Procedure Act). According to the above facts, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of KRW 15% per annum as provided by the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from September 5, 2015, the day following the delivery date of the original copy of the payment order, as sought by the Plaintiff.
Therefore, the plaintiff's claim is justified.