Text
1. The sales contract concluded on June 27, 2012 between the Defendant and B is KRW 30,000,000.
Reasons
1. Facts identical to the description of the cause of the claim as indicated in the attachment of the claim, and as of June 27, 2012, the market value of the instant real estate as of June 27, 2012 is KRW 250 million, and the sum of the maximum debt amount of the right to collateral security established at the time of the instant real estate is KRW 36 million, and the value of the instant real estate provided as joint collateral by the general creditor is KRW 214 million ( KRW 250 million-36 million). The said value and the Plaintiff’s claim for compensation within the limit of the amount of the said claim.
2. Judgment by service (Article 208 (3) 3 of the Civil Procedure Act).