Text
1. The plaintiff's appeal and the conjunctive claim added by this court are all dismissed.
2. After an appeal is filed.
Reasons
1. Basic facts
A. On March 3, 2015, the Plaintiff, the purpose of which is to construct reinforced concrete, was to start rehabilitation procedures on March 3, 2015 by Gwangju District Court 2014 Gohap5024, which was October 10, 2018.
The defendant is a person who conducts a wedding business under the trade name of D.
Standard contract for private construction works (Evidence A No. 2-2)
1. Name of the construction work: New construction work of a DNA store;
2. Construction site: Gwangju Mine-gu F
3. Date of commencement: April 25, 2013: Date scheduled for completion: July 24, 2014 (15 months).
5. Contract amount: 24,500,000,000 won (value-added tax separate) of the instant agreement (No. 1) regarding the construction contract for new construction of the instant securities between the owner of the building and the Plaintiff of the construction project on April 23, 2013, with respect to the permission for the commencement of construction of the instant securities construction project in accordance with the construction permission of the Mine Office for six parcels other than F of Gwangju Mine-gu.
1. The above construction works are not the completion drawings of the buildings that the defendant intends to complete, and the construction drawings that the defendant intends to complete are recognized as being a design, and the construction drawings that the defendant intends to complete are recognized as being in the process of design. If the construction drawings are subsequently finalized, the plaintiff recognizes that the defendant can modify the construction works and the contract.
2. The contract concluded on April 23, 2013 by the Defendant and the Plaintiff set the amount of virtual contract required for the application for authorization and permission, and the Plaintiff recognized that the contract is a contract for the preemptive construction of forest trees and retaining walls before the construction drawing is finalized, and the Defendant and the Plaintiff enter into a separate contract with the retaining wall construction relating to the forest trees and the retaining wall construction.
3. When the final and conclusive construction drawings to be completed are final and conclusive, even if the Defendant selects another construction entity as the contractor of the said construction works in accordance with the terms and conditions set forth in the final and conclusive drawings, the Plaintiff, in addition to the contract amounts arising from forest trees and retaining walls construction works, demands or civilians to any monetary demand against the Defendant.