Text
1. The Defendant’s KRW 111,714,00 for the Plaintiff and KRW 5% per annum from July 26, 2018 to November 29, 2018.
Reasons
1. The parties' assertion
A. The Defendant is obligated to pay the Plaintiff the amount of money stated in the purport of claim 1.5 times the construction cost, since the Plaintiff ordered air conditioners construction among the new construction works for air conditioners located in Incheon po-gun, Incheon, to the Plaintiff, and paid 1.5 times the construction cost at issue when the Plaintiff did not select as a subcontractor. However, the Plaintiff agreed to order air conditioners construction at issue upon the completion of the model air conditioners construction, and even when the considerable time has passed since the model air conditioners construction has not been ordered, the Plaintiff is obligated to pay the Plaintiff the money stated in the purport of claim 1.5 times the construction cost at issue.
B. A stock company B, which is a company executing the new construction works of Defendant Liart, has become a financial problem, and the Defendant, a contractor, takes over the site of Liart and tried to carry out new construction works of Liart by seeking a new construction work.
The defendant will undertake the construction work in consultation with each sewage supplier if only the risk of the year 2018 is exceeded.
The Plaintiff agreed with the Defendant to terminate this construction by the year of 2019, and the Plaintiff agreed to the Plaintiff’s claims with the due date, and the due date has not yet arrived.
2. Facts of recognition;
A. On March 7, 2017, the Defendant: (a) concluded a subcontract agreement including the model summer construction cost, and D forest land construction work (hereinafter “Eriter construction work”) with the amount of 72,270,000 won for model cargo cooling and cooling equipment construction works (hereinafter “system heating and cooling installation”) among the construction works for cooking located in 3,764 square meters in Incheon po-gun, Incheon, Incheon, (hereinafter “Eriter construction work”); and (b) concluded a subcontract agreement with the Plaintiff by determining the period from December 1, 2016 to March 10, 2017; (c) after the site site is selected as the relevant subcontractor for Eriter construction, the Plaintiff is the first negotiating company; and (d) upon entering into a subcontract agreement, the period of validity of this agreement shall be paid 1.5 times the relevant construction cost, if the Defendant did not select as the subcontractor; and (d) the period of validity of this agreement shall be the relevant construction cost after the commencement of the construction and the relevant construction work.