(영문) 부산지방법원 서부지원 2018.05.25 2017가단102059
주차면표기삭제 등
Text

1. The defendant shall be the plaintiff.

A. The 2nd and third floor parking lots of the building indicated in the attached list are the Plaintiff’s members.

Reasons

1. Basic facts

A. Status 1) Buildings listed in the attached list (hereinafter “instant building”)

(2) On December 31, 1994, the Plaintiff obtained a building permit from the head of the Gu having jurisdiction over north-gu, Busan, by obtaining the approval for use on April 12, 200, from the site of the 20th floor above ground, the 6th underground floor below the 6th floor below the 6th underground floor up to the 3rd underground floor, the 4th underground floor up to the 20th underground floor up to the 3rd underground floor. 2th underground. 2) The Plaintiff is an organization of sectional owners (management body) organized pursuant to the Act on the Ownership and Management of Aggregate Buildings for the purpose of managing the 6th and the 6th underground floor above the 6th underground floor and its appurtenant facilities, and the Defendant is an organization management body (management body) organized pursuant to the Aggregate Buildings Act for the purpose of managing the apartment site and its appurtenant facilities.

B. 1) Sale of the instant building: “D apartment reconstruction association” and “E corporation”, the owner of the instant building, are co-owners, and around 1997, the apartment part among the instant building was sold to the Defendant’s members, and the Plaintiff’s members, respectively. 2) Of the instant building, the apartment part among the instant building is ten types and 275 households depending on the type and structure.

In each contract for the supply of the above apartment, the term “building” is written in the “building” column in the “building site” as the “exclusive area, common area, supply area (total of exclusive area and common area), underground parking lot area, contract area (total of supply area and underground parking lot area)”, and the “public land portion” in the “site area” column.

On the other hand, the sale price (supply price) is divided into "building price, site price, and parking lot price" and is marked as "total supply price".

C. The instant building.

arrow