(영문) 수원지방법원 2014.09.25 2013가합1306
공사대금
Text

1. The Defendants shall jointly and severally serve as the Plaintiff KRW 49,354,505 and as a result, from October 1, 2012 to September 25, 2014.

Reasons

1. Basic facts

A. The relationship between the parties 1) The Plaintiff is a company engaged in building work business, civil engineering work business, etc., and D is a person who served as the representative director of the Plaintiff from May 17, 2012. 2) Defendant B Co., Ltd. (hereinafter “Defendant B”) is a company that carries on freezing manufacturing business, special trucking business, etc., and Defendant C Co., Ltd. (hereinafter “Defendant C”) is a company that carries on transportation business, goods freezing storage, warehouse business, etc., and E is a person who actually operates the Defendants.

B. 1) E, such as entering into a contract for new construction of a factory, to D on February 27, 2012, 2012, the F-based Defendants’ factory building B: 1 Dong (1 & 2nd floor), factory (1/2nd floor), 3 Dong factories: 2 Dong (1 and 2nd floor), factory (2nd floor), 4 Dong-new construction of security room (hereinafter “instant construction”).

A) A contract period of KRW 1,600,000 (excluding value-added tax, KRW 960,00,000,000 for the construction of a factory building in Defendant B, and KRW 640,00,00 for the construction of a factory in Defendant C’s factory building in Defendant C) is the order of work, and the Defendants are the order of work, as follows, AD Integrated Construction Co., Ltd. (hereinafter referred to as “AD case”) by leasing a comprehensive construction license and name to D (hereinafter referred to as “AD case”).

(1) The term “construction area” under Article 19(1) of the General Conditions of the Contract for Private Construction Works (Adjustment of Contract Amount due to Modification of a Design). The term “construction area” under Article 19(1) of the General Conditions of the Contract for Construction Works: Defendant B’s Construction Work (Construction Area: 1860m2,32m2: 186m2,200: The construction area: the construction period: the F (3) construction period: the starting date - the completion of February 27, 2012 - the contract amount of KRW 1,056,00,000 (including additional taxes): the supply price of KRW 960,000,000 for value-added tax of KRW 96,000,000,000 for value-added tax (including the adjustment of contract amount due to modification of a design) if the contents of the design do not coincide with the condition of the construction site, or if there is any uncertainty, omission, or error in the construction work, or it is required to install additional facilities.