(영문) 서울동부지방법원 2017.11.29 2015가합103140
공사대금
Text

1. Of the instant lawsuit, the part on the claim against Defendant B, E, F, and H and the part on the primary claim against Defendant D and G are all parts.

Reasons

1. Basic facts

A. The contract for construction works between the instant association and I and the Defendants’ joint and several sureties 1) J Urban Environment Improvement Association (hereinafter “the instant association”) is the instant association.

) The construction of the main complex apartment and its ancillary facilities on the plot of land, Kuyang-gu, Yangyang-gu, Kuyang-gu, and 36 (hereinafter referred to as “instant construction”).

L Co., Ltd. (formerly changed on December 18, 2014): I Co., Ltd. and I (hereinafter “I”) on December 15, 2010

) The instant contract was concluded with the J. The instant agreement was written between the instant association (A) and I (B) on December 15, 2010, and on April 19, 2012, “the construction contract entered into on April 19, 2011”.

The following shall be entered into: (a) partially adding, amending, and amending a construction project contract concluded on January 24, 2013;

Except as otherwise expressly provided for in this Agreement, the existing contract and the modified contract shall apply mutatis mutandis.

- - Future -

5. Business method: B shall be 74,311,00,000 won (including value-added tax) and project expenses shall be 12,92,560,000 won (including value-added tax) on the condition that Party A and its members complete the construction work set forth in subparagraph 4 on the land owned by Party A and its members.

The appropriation for the construction cost of KRW 74,311,00,000 and the project cost of KRW 12,92,560,000 for the loan of KRW 74,31,000 and the project cost of KRW 12,92,560,00 for the loan of KRW 15,00 for the loan of KRW 74,31,00 for the loan of KRW 74,00 for the loan of KRW 5,00 for the loan of KRW A and the sales proceeds of the share of KRW 252 for the general apartment unit of KRW 252, the sales

Provided, That where the total amount is different from the project cost of 12,92,560,00 won between A and B until the obligation under this contract is completed, A and B shall be settled for the increased or decreased portion, and the total amount of the project cost and the project cost shall be adjusted in the same manner as the total amount of the purchase price of cash and equity goods is paid.

(Payment method of cash: Payment by the general sale price in commercial buildings (Incidental expenses).