1. The Defendants are 54,00,000 won to each Plaintiff and 18% per annum from August 1, 2016 to the day of full payment.
Reasons
According to the purport of Gap evidence Nos. 1 through 3 and the entire pleadings, the Plaintiff loaned the Defendants the interest rate of KRW 64 million in total, including KRW 10 million on January 21, 2014, KRW 10 million on February 28, 2014, KRW 10 million on March 3, 2014, KRW 4 million on May 14, 2014, KRW 10 million on June 27, 2014, KRW 64 million on October 26, 2014, and KRW 10 million on September 16, 2015, and the Plaintiff failed to pay interest rate of KRW 10 million on September 25, 2015.
According to the above facts of recognition, the Defendants are obligated to pay each Plaintiff KRW 54 million (i.e., KRW 64 million - KRW 10 million) and damages for delay calculated by the rate of 18% per annum, as claimed by the Plaintiff, from August 1, 2016 to the date of full payment.
Thus, the plaintiff's claim against the defendants is justified, and this is accepted.