logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울남부지방법원 2017.10.13 2015가합103983
청구이의
Text

1. As to the Defendant:

A. Part 2010 tea506 of this Court, and a succession clause of this Court.

Reasons

A. In light of the above legal principles, the Plaintiff Union and the Plaintiff Union and the Plaintiff Union and the Plaintiff Union and the Plaintiff Union and the Plaintiff Union signed a subcontract between the Plaintiff and the United Nations Construction Co., Ltd. (hereinafter “YY”) on February 19, 2008.

between A and A market main reconstruction work (hereinafter referred to as “instant reconstruction work”).

The contract for construction works was entered into with respect to this case, and the main contents relating thereto are as follows:

1. Project name of the contractor: A project to create a major complex of a project for reconstruction of the A market;

2. Construction site: Within Yangcheon-gu Seoul Metropolitan Government;

3. Scheduled date of commencement: Within 15 days from March 5, 2008 or from the date of submission for commencement.

4. The scheduled completion date: 20 months from the commencement date.

5. Contract amount of construction work: A total sum of 12,00,000 won per day (12,00,000,000 won) - Value-added tax shall be separately imposed.

6. Contract guarantee method: Submission of a performance bond of KRW 4 billion in the amount equivalent to one-third of the contract amount of the work.

8. Construction cost: The payment of residential facilities (32 square-type apartment*32 households) - The contractor's defined shares, Article 5 (Method of Guarantee for Contract) 1, 100,000 shall issue a performance bond as provided for in paragraph 6 of Article 1 and submit it to the plaintiff association by the scheduled date of commencement of this construction in order to guarantee this construction contract.

(2) The performance bond under paragraph (1) shall be a letter of guarantee issued by the following agencies:

1. Certificates issued by each mutual-aid association under Article 54 (1) of the Framework Act on the Construction Industry;

2. A guarantee certificate issued by an equivalent institution, such as a guarantee insurance company and the Korea Credit Guarantee Fund, shall be treated at the construction site in accordance with relevant Acts and subordinate statutes, and the Plaintiff Association shall reflect the expenses incurred in disposing of wastes in the contract amount;

Article 21 (subcontract, etc. of Construction Works) (1) Where it is intended to subcontract the construction work contracted to a third party, the subcontractor shall be selected as prescribed by the Framework Act on the Construction Industry.

arrow