(영문) 청주지방법원충주지원 2016.11.17 2016가단3914
대여금
Text

1. The defendant shall pay to the plaintiff KRW 401,861,230 and KRW 218,00,000 among them, from June 8, 2016 to the day of full payment.

Reasons

1. Basic facts

A. The Plaintiff extended interest of KRW 4.51% per annum on November 9, 2007, KRW 145,000,000 per annum, and KRW 4.11% per annum on September 26, 201, and KRW 10,000 per annum on September 26, 201, and KRW 4.11% per annum on December 9, 201, and KRW 4.11% per annum on April 11, 201, ④ interest rate of KRW 20,000 per annum on January 12, 201, ⑤ interest rate of KRW 30,000,00 per annum on April 24, 201, calculated the interest rate of KRW 22% per annum on April 11, 201, and calculated the interest rate of KRW 10,00 per annum on June 30, 2014, respectively.

(hereinafter “instant loan”).

B. The Defendant, from September 2015, lost the benefit of the term due to the Defendant’s failure to pay interest on the instant loan obligations. On June 8, 2016, the amount of the loan unpaid as of June 374, 193,040 won (6.10,000 won out of the above loan, 60,000 won paid in part, and 106,193,040 won, and the remainder of the loan remains at all) and interest or delay damages (27,68,190 won, 401,861,230 won (i.e., 374,193,040 won, 27,668,190 won, 27,668,190 won). The damages for delay at the rate of 106,50,000 won per annum 1541,500,000 won per annum (6).

[Ground of recognition] Unsatisfy, entry in Gap evidence 1 through 4 (including each number for a case with a serial number), the purport of the whole pleadings

2. The assertion and judgment

A. According to the above facts finding as to the cause of the claim, barring any special circumstance, the Defendant shall pay to the Plaintiff KRW 401,861,230 of the principal and interest of this case, and KRW 218,00,000 of the principal and interest of this case ( KRW 145,000,0000, KRW 13,0000,000, KRW 20,0000, KRW 30,000,000, which is the agreed interest rate of KRW 22% per annum from June 8, 2016 to the date of full payment ( KRW 106,193,040, KRW 19541 per annum from June 8, 2016 to the date of full payment).