(영문) 창원지방법원통영지원 2016.09.08 2014가합1634
지체상금 등
Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 286,146,172 to the Plaintiff (Counterclaim Defendant) and its related amount from June 11, 2016 to September 8, 2016.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. Facts of recognition;

A. The Plaintiff is a company that performs construction works and civil engineering works.

The defendant is a person who runs a construction business in the name of "B".

B. On October 19, 201, the Plaintiff and the Defendant entered into a subcontract with the Defendant at KRW 1-2: KRW 20,000,000 for the construction period of KRW 20,000 for the C Housing Complex (hereinafter “1-2 new construction”); KRW 20,000 for the construction period of KRW 20,00 for KRW 30,00 for the construction period of KRW 20,00 for KRW 20,000 for the first 20,000 for the first 20,000 for the first 20,000 for the first 30,000,000 for the first 20,000 for the first 20,000 for the construction period of KRW 30,00 for the first 20,000 for the first 20,000 for the second 20,000 for the second 30,000,000 for the second 20.