(영문) 서울중앙지방법원 2018.12.03 2018가단5049822
양수금
Text

1. The Defendants are jointly and severally liable to the Plaintiff for KRW 273,653,809 and KRW 91,568,570 among them, from February 14, 2008 to April 4, 2008.

Reasons

Comprehensively taking account of the overall purport of the statements and arguments in Gap evidence 1 through 3 and Eul evidence 1 through 5, the plaintiff filed a lawsuit against defendant Eul corporation and Eul on May 28, 2008 with the Seoul Central District Court 2008Da65769, and filed a lawsuit on the claim for the amount of money transferred on May 28, 2008, "the defendant jointly and severally paid to the plaintiff 273,653,809 won and 91,568,570 won a year from February 12, 2008 to April 4, 2008, 19% a year from the next day to the date of full payment, and the above judgment was finalized on July 19, 2008, D received the approval of inheritance from the spouse and children of the plaintiff, CF, D's inheritance, and C-1, 281, 208, 208, 2018.

Therefore, the defendants are jointly and severally liable to pay to the plaintiff 273,653,809 won and damages for delay calculated at the rate of 19% per annum from February 14, 2008 to April 4, 2008 and 20% per annum from the following day to the date of full payment.

The plaintiff's claim against the defendants is accepted.