(영문) 수원지방법원 2018.08.09 2018고단552
국토의계획및이용에관한법률위반등
Text

Defendant

A shall be punished by imprisonment for eight months and by a fine for 5,00,000 won, and Defendant B shall be punished by a fine for negligence of 10,00,000 won.

Reasons

Punishment of the crime

1. Defendant A is a director and constructor in-house company B, a construction business chain company B, and the actual owner who conducts development activities for electric source housing C (D prior to the change) in the wife population in Young-si.

(a) Where a person intends to change matters for which permission for development acts in violation of the National Land Planning and Utilization Act has been obtained or to change the form and quality of land, he shall obtain permission from the competent authority

Nevertheless, the Defendant changed the form and quality of land by performing construction works for roads, amnestys, and electric house construction sites (project owner F) with respect to the wife population C, 4,524 square meters (project owner E) and 4,898 square meters (project owner F) in a permitted area for development activities from around December 2, 2016 to May 2017, which is a permitted area for development activities.

(b) A person who intends to divert a mountainous district in violation of the Management of Mountainous Districts shall determine its use and obtain permission from the head of the relevant forest agency, etc. according to the classification of the types, areas, etc. of the mountainous district prescribed by Presidential Decree,

Nevertheless, the Defendant, without permission to change the use of mountainous districts by the head of a forest office, etc. from around December 2, 2016 to May 2017, 713.32 square meters of the permitted area for the said forest land (project owner E), was newly built, damaged prevention facilities, retaining retaining walls, etc.

(c)

(1) Violation of the Building Act (1) Any change in the matters permitted or reported by a building owner before permission for change shall be permitted or reported by the competent authority.

From December 2016 to May 2017, the Defendant changed the building area of 66.40 square meters, total floor area of 498.40 square meters, total floor area of 498.40 square meters, and total floor area of 713.32 square meters, total floor area of 1,93.62 square meters, main building building 15 square meters, and 13 single-unit houses, which are single-unit houses, the building owner E obtained permission.

The defendant shall make a change in the above forest land.