Text
1. Defendant (Appointed Party) and Appointed D are as follows: (a) each Plaintiff’s KRW 260,000,000; and (b) December 31, 2010.
Reasons
1. Basic facts
A. The background of the instant apartment project 1) The E Co., Ltd. (hereinafter “E”) that entered into an execution agency contract
) From around 2002 to promote a project to build a collective housing in this region through the establishment of a regional housing association after removing the housing of the Franc City from residents, purchasing the land from the residents. On May 10, 2002, G Housing Association is to be implemented on May 10, 2002, and Korea Industrial Development Co., Ltd. (hereinafter referred to as the “Bsan Construction Co., Ltd”) (hereinafter referred to as the “instant apartment”) is to be changed to the two industry development Co., Ltd. (hereinafter referred to as the “Bsan Construction Co., Ltd.”) into the City of 523 households in total (hereinafter referred to as the “instant apartment”).
2) According to the above implementation agency contract, E recruited union members (However, at the time of recruiting union members, the name of the housing association was "I housing association".
(1) On November 7, 2002, the Korea Industrial Development Corporation, which was a Si construction, constituted G housing association with the authorization of the establishment of the association from the Siang City on November 7, 2002, constituted a second-lane G housing association on January 15, 2003, and constituted G third-lane G housing association on September 10, 2004 (as the Korea Industrial Development Corporation, which was a Si construction, was acquired at 2004, each of the said associations changed the name of each association into H 1 regional housing association, H 2 regional housing association, and H H 3 regional housing association on April 12, 2007.
“The instant associations” refers to “the instant associations.”
(B) Although the instant association was formed as above, E had kept one seal in the name of the president of the instant association and one seal in the name of the president of the I Housing Association until February 28, 2007, when the sales contract for the instant apartment was concluded to perform the business affairs under the above enforcement agency contract.
3) The approval of the project plan and the progress of the project thereafter) E shall be located on June 1, 2006 upon the application for the approval of the project plan on June 24, 2005.