Text
1. The defendant's appeal is dismissed.
2. The costs of appeal shall be borne by the Defendant.
Purport of claim and appeal
1...
Reasons
Basic Facts
The plaintiff is a company that aims at the information and communications construction business, and the defendant is a religious organization that aims at training and education for leaders, religion, and teaching.
On February 27, 2016, Defendant D (Representative D I) entered into a contract with Defendant C (Representative H; hereinafter “C”) on the condition that, with respect to the “Energy-saving Project” of each inspection in the Daejeon Northern area under the jurisdiction of the Defendant, C, upon determining and submitting the construction volume of each inspection, the construction contract between Defendant C and each inspection.
The main contents of the above contract shall be as follows, with respect to each inspection energy saving project under the defendant's command (hereinafter referred to as "A") and C (hereinafter referred to as "B") with respect to each inspection energy saving project under the defendant's command (hereinafter referred to as "project"), this contract shall be prepared for mutual interest and efficiency.
1. All temples and teaching staff located in the area north of Daejeon (Seoul Special Metropolitan City, Incheon Metropolitan City, Gyeonggi-do, and Gangwon-do) under the jurisdiction of the defendant subject to "project";
2. 1) Scope of “project”: 1) Replacement and 2) Replacement of old electric wires and replacement and installation of CCTVs 3) - Other matters requested by inspection, such as improvement of old convenience facilities, etc.
3. A’s duty 1) A’s “project” shall submit a field inspection plan for each inspection of “project” to “A” and “A” shall notify “B” of the document or verbal inspection schedule of “B” to the inspection subject to the actual inspection of “B” and shall notify “B” after confirming the actual inspection schedule of “B”. “A” shall determine and notify the actual inspection schedule of “B” within seven days from the date of submission of the actual inspection plan of “B”.(2) The review of “project” and the estimate and confirmation “B” shall be submitted to “A” each inspection prepared on the basis of the actual inspection.