(영문) 청주지방법원 2019.02.28 2017가단113174
손해배상(기)
Text

1. The plaintiff's main claim is dismissed.

2. The Defendant: (a) KRW 122,178,000 for the Plaintiff and its related expenses on December 22, 2017.

Reasons

1. Basic facts

A. C around June 2016, at the recommendation of D, set up a camping site on the 20th E and one parcel of land outside Mt. D (hereinafter “instant land”). Around June 16, 2016, upon D’s introduction, the Plaintiff agreed to entrust the Defendant with the affairs of establishing the F Camping district unit plan of KRW 1,50,000,000,000,000 from the service price to the Defendant’s account. B around June 20, 2016, C transferred KRW 60,000,000 from the service price to the Defendant’s account. Around September 20, 2016, the Plaintiff established a 2000,0000,0000,0000,0000,0000,000,0000,0000,0000,000,000,000,000.

E. After receiving a notice from D that the district unit plan for the instant camping site was approved, the Plaintiff paid KRW 30 million in total as compensation for removal and resettlement of the instant land from April 27, 2017 to June 8, 2017, and KRW 10 million in the purchase price of landscape trees around July 3, 2017, and around August 3, 2017, the Plaintiff was affected by camping accommodation and ancillary facilities installation costs of KRW 5 million in total and the camping site.

arrow