(영문) 인천지방법원 2019.11.14 2019구합51318
액화석유가스충전사업 허가신청 불허가처분 취소 청구의 소
Text

1. The Defendant’s disposition of non-permission to file an application for permission for liquefied petroleum gas filling business with the Plaintiff on October 4, 2018 is revoked.

2...

Reasons

1. Details of the disposition;

A. On February 14, 2001, pursuant to the Act on Special Measures for Designation and Management of Development Restriction Zones (hereinafter “Development Restriction Zones Act”), the Defendant: (a) formulated a “plan for the placement of liquefied petroleum gas charging stations for automobiles within the south-gu Incheon Metropolitan City, Nam-gu, and publicly announced as E for the installation of one filling station for automobiles in the two directions of the section B located within the development restriction zone within the jurisdiction of Nam-gu, Incheon (date of time: Nam-gu, Incheon; Dadong-gu, Incheon; 6km; hereinafter “instant road”); (b) and (c) obtained permission for the installation and operation of the I filling station on land within the development restriction zone adjacent to the instant road in the direction of both directions of the instant road; and (d) obtained permission for the installation and operation of the I filling station on land within the Nam-gu, Incheon, Nam-gu, and the direction of installation and operation of the roads (hereinafter “the instant plan”).

On December 29, 2017, the Minister of Land, Infrastructure and Transport approved an industrial complex (K industrial complex) plan with respect to 233,141 square meters of land located within the development-restricted zone adjacent to the instant road, which is located within the development-restricted zone adjacent to the instant road, and publicly notified as L of the Ministry of Land, Infrastructure and Transport on December 29, 2017, the Mayor of Incheon Metropolitan City announced as M of Incheon Metropolitan City by determining an urban management plan to cancel the development-restricted zone from the development-restricted zone with respect to 233,141 square meters of land located within the relevant development-restricted zone. Accordingly, the H land located in the Incheon Nam-gu Incheon Metropolitan City, which is the site of the said IMO Electric Complex, was released

On December 20, 2018, the Korea Land and Housing Corporation, which is the executor of the above industrial complex project, completed the registration of transfer of ownership based on consultation on public land for land H and building on the land of Nam-gu Incheon Metropolitan City, which is the site of the above I Electric Complex.