Text
1. The Defendants jointly share KRW 22,300,000 to the Plaintiff and the period from November 11, 2012 to September 23, 2014.
Reasons
1. As to the claim against Defendant B
A. 1) On September 23, 2012, the Plaintiff is the Defendant Company B (hereinafter “Defendant Company”).
(A) The interior funeral construction contract (hereinafter “instant principal contract”) with the size of 85 square meters in the fourth floor area of a building that is newly constructed on the ground of Gangseo-si D with the following contents as follows:
A) The construction period was concluded. The construction period was between October 10, 2012 and November 10, 2012: indoor air conditioners and indoor air conditioners, rest rooms, books, and new air conditioners: 74,00,000 won: the date of concluding the contract, the second down payment of KRW 22,200,000,000, which is the date of commencement of construction work, and the second down payment of KRW 22,29,60,000,000, which is the date of commencement of construction, the first remainder of KRW 7,40,000,000, the remainder of KRW 1,200,000, the remainder of KRW 7,40,000, the remainder of KRW 27,400,000, the remainder of KRW 1,200,0000, each of the Plaintiff’s new deposit account, the date of commencement of construction work, and the Plaintiff’s payment of KRW 30,2000, each of Defendant 20.
3) On October 17, 2012, the Plaintiff remitted the intermediate payment of KRW 29,600,000 to the F’s account upon Defendant C’s request. 4) Upon Defendant C’s request, the Plaintiff paid KRW 5,500,000 to the global system as the payment for air conditioners installed three times from November 3, 2012 to May of the same month.
5) On November 16, 2012, the Plaintiff remitted the first balance of KRW 7,400,000 to G’s account upon Defendant C’s request. 6) On November 23, 2012, the Plaintiff paid KRW 6,00,00 to the Defendant Company: (a) the Plaintiff paid KRW 6,00,00 to the Defendant Company as additional construction costs, etc. for the Plaintiff’s alteration to the wood structure construction; and (b) the Defendant Company completed the process of more than 90% so that the Plaintiff may suffer exposure until November 28, 2012; (c) the Plaintiff did not have to pay additional construction costs to the Defendant Company (hereinafter “the instant additional contract”); and (d) the Defendant Company on June 24, 2016.