Text
1. The Defendants deliver to the Plaintiff the buildings listed in the attached list.
2. The costs of lawsuit shall be borne by each person;
3...
Reasons
1. The administrative disposition plan on the A-area Housing Redevelopment Improvement Project implemented by the Plaintiff in the Nam-gu, Busan, on August 2, 2013, which was approved on August 7, 2013, and announced publicly on August 7, 2013. The Plaintiff deposited the compensation for the Defendants on May 1, 2015 following the Busan Regional Land Tribunal’s ruling on March 16, 2015, as the Plaintiff deposited the compensation for the said losses with the Defendants on May 1, 2015, the Plaintiff is a co-owner of the real estate listed in the separate sheet located in the said rearrangement project zone, and is against the Defendants, who are subject to cash liquidation under Article 49(6) of the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents.