(영문) 서울중앙지방법원 2017.09.05 2014가합585445
보험금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. The Plaintiff is a company established for the purpose of carrying on shipbuilding business, etc., and the Defendant is a corporation established based on the Act on the Indemnification for Fire-Caused Loss and the Purchase of Insurance Policies, which aims at governmental agencies and defense industry-related insurance business.

B. On June 13, 2012, the Plaintiff entered into a shipbuilding contract with the Defense Acquisition Program Administration under the Ministry of National Defense for three subsequent boxes (16, 17, and 18 boxes).

C. Among the equipment installed by the Plaintiff in the said vessel, there are equipment installed by the Plaintiff after being provided by the Defense Acquisition Program Administration (hereinafter “government-funded equipment”). On June 13, 2013, the Plaintiff and the Defendant entered into an assembly insurance contract with the Defendant as the insurer in relation to the assembly of government-funded equipment, and the Plaintiff and the Defense Acquisition Program Administration as the insured (hereinafter “instant insurance contract”). The main contents of the instant insurance contract are as follows.

Section 1 of the detailed insurance period (the corresponding provisions related to the period of security) from May 9, 2013 to December 1, 2014 (including the 10-day test period) the amount of insurance coverage for physical damage insured items in Section 1.

1. prefabricated 1-1. Items 1-2. Security for third party's liability of compensation 1-3. Expenses for assembly;

2. Civil engineering works;

3. Expenses for the removal of residues;

4. KRW 153,966,128,000- (CSL 1,000,000,000-) property located within the facility or a construction site of the ordering person as property owned, protected, managed, or controlled by the ordering person: 50,000,000 of the Won for the manufacturer's defects and/or the test as to the test; 500,000,000 of the Won for the natural disaster/manufacturer's defects and/or other risks; 50,000,000,000 of the Won for the other risks of the accident; 153,96,128,000-1,000-1, the total amount of the insurance coverage at the first sector, KSW 153,966,128,000-D 1,000, 100,000,000 for self-charge, 10,0005,000