(영문) 서울북부지방법원 2016.12.15 2015가단103286
손해배상(산)
Text

1. From May 26, 2014 to December 15, 2016, KRW 6,239,166 to the Plaintiff, DNA Co., Ltd.

Reasons

1. Occurrence of liability for damages;

(a) Basic facts 1) Defendant Treatment Line Marine Co., Ltd. (hereinafter “Defendant Treatment Line Marine”)

) The company is engaged in the business of manufacturing maritime structures, ships, etc. in the 337 shipbuilding yard as a result of the macroscopic scopic scopic scopic scopic scopic scopic scis

(2) As a partner of the Defendant Daewoo Shipbuilding’s Sea, the Plaintiff was a company that was awarded a contract for electric firer work, posing work (the installation of cables), string work (the connecting of the installed cables, lighting, location, and communications equipment) on the inside of the vessel under construction of the Defendant Daewoo Shipbuilding’s sea. The Plaintiff entered into an employment contract on May 20, 2014 and entered into an cable relay work on the part of Defendant DNA for cable relay work. (2) On May 17:20, 2014, the Plaintiff suffered from the 337 marine structure as of May 26, 2014, the Plaintiff: (a) completed cable relaying work at cella in the 337 marine structure; and (b) completed the cable relay work at the string of the left side (hereinafter referred to as “instant accident”); and (c) caused the Plaintiff’s injury to the salke, salkeing of the salke in the left side.

3) The Plaintiff filed an application for industrial accident management due to the instant accident. The Plaintiff rejected the industrial accident management with the Korea Workers’ Compensation and Welfare Service on the ground that the circumstance leading up to the Plaintiff’s accident was unclear. However, the Plaintiff obtained approval from the Korea Workers’ Compensation and Welfare Service for occupational accidents on the ground that it was an accident that occurred in the course of performing his/her duties under an employment contract in his/her workplace during his/her business hours, and the Plaintiff received insurance benefits of KRW 7,199,50,000 as temporary layoff benefits for the treatment period from June 24, 2014 to October 22, 2014 from the Korea Workers’ Compensation and Welfare Service, and received KRW 13,090,00 on June 450, 2014 as compensation for damages from the UN.