(영문) 서울남부지방법원 2017.11.22 2017고단941
근로기준법위반등
Text

A defendant shall be punished by imprisonment for one year.

However, the execution of the above sentence shall be suspended for a period of two years from the date this judgment became final and conclusive.

(e).

Reasons

Punishment of the crime

The Defendant, as the representative director of the O Co., Ltd. in Geumcheon-gu Seoul Metropolitan Government N. 604, is the employer who executed electrical construction with 40 full-time workers at the site of the Jeju-si New Airport Construction, the R&C construction in Jeju Q, and the Jeju-si New Apartment Construction Work.

When a worker dies or retires, the employer shall pay the wages, compensations, and other money or valuables within 14 days after the cause for such payment occurred.

From August 10, 2015 to March 31, 2016, the Defendant served at the construction site of the new apartment complex at the Jeju-si from August 10, 2016, and did not pay KRW 3,90,000,00,00 for retired workers within 1,2,4,56,8 through 13, 15, 16, 17, 22, 23, 26 through 29, and 20, the sum of the wages of 52,120,250,000 each, within 14 days from the date of retirement without an agreement on the extension of the payment date between the parties.

The defendant of "2017 Highest 3537" is the representative director of theO established for the purpose of construction business, etc.

The Defendant, from March 2015 to August 201 of the same year, received installation of a lighting control system from the victim V, who is the representative of the U of the (State), and did not pay 30,300,000 won, which is a part of the construction cost. On April 2016, the Defendant again made a false statement to the Defendant that, “The Defendant would pay to the Defendant the payment without any mold up to the price that is not paid before the Jeju company installed lighting control system equipment to construct the X apartment newly constructed in the south-do.”

However, from the end of 2015, the financial situation of the company has aggravated, and at the time of around April 2016, the amount of unpaid materials for various material companies has reached 1.4 billion won, and there was a seizure of construction price from the material company, and the amount of unpaid materials has already been equivalent to 600 million won, which had been held by a private person Y (ju).