Text
1. The plaintiff (Counter-Defendant) shall dismiss his primary claim.
2. The Defendant-Counterclaim Plaintiff (Counterclaim Defendant) is the Plaintiff-Counterclaim Defendant on 292,907.
Reasons
1. Basic facts
A. On June 16, 2010, the Plaintiff entered into a sales contract between the Plaintiff and the Jae-young character company. On June 16, 2010, the Plaintiff concluded a sales contract between the Plaintiff and the Plaintiff (hereinafter “instant sports facility site”) with the land for sports facilities (golf) located within the Cheong-si Housing Site Development Project, 266-3 Sports Site 294,198 square meters and 266-4,66 square meters (hereinafter “instant sports facility site”).
(2) The Plaintiff promised that “A purchaser shall bear expenses incurred in creating forest replacement resources when he/she obtains permission for conversion of a site for sports facilities pursuant to the Mountainous Districts Management Act by June 30, 201, which is the scheduled date of completion of the project in the second phase area of the housing site development project after consultation with the Plaintiff.”
3) Jawals Co., Ltd. (hereinafter “Sawals”)
(4) On July 8, 2010, the Plaintiff and the Plaintiff concluded a sales contract with the content that the instant sports facility site was purchased on or after December 1, 2009, including the purchase price, 21.1 billion won, and the time when the land was available. Under the above sales contract, the contract deposit was paid on the date of the contract, and the remainder of the purchase price was agreed to be paid in installments on or after ten occasions from January 8, 201 to July 8, 2015. 4) The re-B-B-B-E was partially modified on or after September 4, 2012 as a plan to promote the business of newly constructing and selling the golf telecom in connection with the instant sports facility site.
The Plaintiff entered into a sales contract with the Plaintiff, on December 1, 2009, on a purchase price of 15.68 billion won, and after December 1, 2009, on a purchase price of 15.68 billion won, and on a price of 19376 square meters and 1485 square meters (hereinafter “the instant detached house site”).
The sales contract of this case is "the total of the sales contract of this case".
The contract deposit under the above sales contract shall be paid on the date of the contract, and the remainder of the purchase price shall be ten times from March 13, 201 to September 13, 2015.