(영문) 춘천지방법원 강릉지원 2018.02.21 2017고단778
업무상과실치사등
Text

Defendant

A In four months of imprisonment without prison labor, Defendant E shall be punished by imprisonment for four months, Defendant B shall be punished by imprisonment for six months, Defendant C Co., Ltd.

Reasons

Punishment of the crime

【Basic Fact-finding Co., Ltd. was a corporation established for the purpose of re-construction business, etc. with L 4th floor L 3, Samcheon-si, and subcontracted “N installed construction work” among the above construction work to F. Co., Ltd., Ltd., a corporation established for the purpose of manufacturing, etc. located in Kimhae-siO, under a subcontract for construction of N during the instant construction work, and directly manufacture of materials necessary for installation of the said N., but the manufacturing of materials, such as cutting of steel structures, and installation of cable railways (hereinafter “N-based and upper construction”), which used the basic construction work for the installation of N., such as cutting of rock walls and ceiling, etc., and the construction work of underground upper parts (hereinafter “N-based and upper construction work”), which took place on Oct. 20, 2016 at the time of re-subcontracting to D Co., Ltd., Ltd., and the construction work of construction business and upper parts, which took place on Oct. 20, 2016, 2000

[Criminal Facts]

1. Defendant B and Defendant A’s joint crime is the representative of D Co., Ltd. who performs the N’s foundation and upper construction, and Defendant A is the safety and health manager of the said construction. The business owner’s interest performing the instant construction works is a person in charge of safety and health management at the site of the instant construction site by re-subcontracting the N foundation and upper construction to the said Co., Ltd. in relation to the instant construction works.

On November 8, 2016, the Defendants were engaged in crushinging work at RR level in the construction site of this case, which is in progress at Rriwon at Rriwon-si around 13:14 on November 8, 2016.

A business owner shall rain, snow, wind, or otherwise.