Text
1. The defendant shall be the plaintiff.
(a) deliver Jongno-gu Seoul Metropolitan Government No. 201;
(b) 2,745,910 Won and its 2,487.
Reasons
On October 28, 2010, the Plaintiff leased the instant building as stated in the Disposition No. 1 (hereinafter “instant building”) to the Defendant with a deposit of one million won, KRW 800,000 per month, and the period from November 18, 2010 to November 17, 2012 (hereinafter “instant lease contract”). The Defendant paid late payment charges at the rate determined by the Plaintiff at the time of delinquency in rent, and the Defendant agreed that the contract may be terminated if the Defendant was in arrears for three months or more. The Defendant delayed payment from December 2010, and on this ground, the duplicate of the instant complaint, which contains the Plaintiff’s declaration of termination of the instant lease contract, reaches the Defendant on February 13, 2014, and thereafter, the Defendant did not pay part of the rent and late payment charges to the Defendant and paid the late payment charges to the Defendant, and thus, the amount of late payment charges to the Defendant is equivalent to KRW 180,84,278,2014.
According to the above facts, the lease contract of this case was terminated on February 13, 2014. Thus, the defendant is obligated to deliver the building of this case to the plaintiff and pay to the plaintiff 2,745,910 won (2,487,200 won, including rent, etc., 258,710 won) and 2,487,200 won, including rent, etc. among them. Accordingly, the plaintiff is obligated to pay damages calculated at the rate of 20% per annum from September 18, 2014 to the day of complete payment, which is clear after a duplicate of the application for modification of the claim of this case and the cause of the claim of this case, to the day of complete payment, and to pay damages for delay calculated at the rate of 80,000 won per month from September 1, 2014 to the day of complete delivery of the building.
Therefore, the plaintiff's claim is justified and accepted.