Text
1. The Defendant’s KRW 21,80,000 as well as the Plaintiff’s KRW 6% per annum from July 27, 2016 to June 2, 2017, and from June 3, 2017.
Reasons
1. Basic facts
A. On October 28, 2015, the Plaintiff concluded a construction contract with the Defendant and the C&W sports hub as the construction period for the overall production and supply of program sets (including value-added tax) from November 1, 2015 to December 28, 2015; and the construction cost of KRW 41,80,000 (including value-added tax).
B. The plaintiff is the above A.
The construction work has been completed in accordance with the construction contract stated in the Paragraph, and the Defendant paid the Plaintiff KRW 20,000,000,000 as the construction cost on November 11, 2016, and KRW 10,000,000 on January 26, 2017.
[Grounds for recognition] Gap evidence Nos. 1 through 4, the purport of the whole pleadings
2. According to the above facts of recognition, the Defendant is obligated to pay to the Plaintiff the remainder of the construction cost of KRW 21,800,000 and damages for delay calculated at the rate of 6% per annum prescribed by the Commercial Act from July 27, 2016 to June 2, 2017, which is the day following the delivery date of the complaint, as the Plaintiff seeks, from July 27, 2016 to June 2, 2017, and from June 3, 2017 to the day of full payment.
3. Conclusion, the claim of this case is accepted on the ground of the reasons.