Text
1. The Defendant’s KRW 203,542,596 for the Plaintiff and KRW 6% per annum from June 12, 2014 to May 14, 2015.
Reasons
1. Basic facts
A. On October 4, 201, the Plaintiff: (a) constructed the instant construction work on the sloping roof of reinforced concrete structure (hereinafter “instant construction”); (b) 480,000,000 won (where value-added tax is included, value-added tax shall be included) on the ground of 264.1 square meters on the ground of 264.1 square meters from the Defendant of Ansan-si, Ansan-si; (c) 480,000 won (hereinafter “instant construction work”).
[] A contract for construction works to be contracted was concluded (hereinafter “instant contract”).
(b) Contract agreement on construction works;
1. Construction name: New construction of commercial housing;
2. Construction site: Members of Ansan-si in Gyeonggi-do (A7-2).
3. A construction period: Six months from the actual commencement date (priority application of special-purpose items).
4. Contract bond: Value of supply of the company million won: Value-added tax of the company0 million won: 10 percent of the value-added tax (10 percent of the value of supply).
7. The rate of liquidated damages for delay: 1/10,000 per number of days of delay.
8. Interest rate for delayed payment: (a) On October 4, 2011, 19% per annum; (b) B beneficiaries of the construction project (hereinafter “owner”; (c) Article 3 (General Conditions for Contract for Construction Works; (d) the contract amount of the construction project shall be the amount calculated by multiplying the horizontal unit price by the total floor area authorized by the competent authority on the basis of special conditions for addition; and (e) where there is an increase or decrease in the area, it shall be adjusted to the unit price per square meter according to the design and construction area (only after consultation, it shall be adjusted to the usual unit price); (d) the annual unit price of 492 square meters: 149 square meters: three million square meters: (VT separate) the construction amount; (e) Article 4 (Period of Construction Works); (g) the construction period shall be within eight months from the date on which the removal of obstacles was submitted or the date on which the construction work is commenced; and (e) the construction period shall not be changed to Gap’s direct management due to the relevant laws and regulations.