(영문) 서울중앙지방법원 2019.07.25 2019가단5113812
시행중인 공사 중단과 원고 피해보상
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. The Plaintiff’s assertion is a person who resides in a house located in Jung-gu Seoul Metropolitan Government (hereinafter “instant house”), and the Seoul Urban Infrastructure Headquarters under the Defendant’s jurisdiction is responsible for a renovation project consisting of a project operator, Seoul Special Metropolitan City Mayor, the construction period from August 31, 2017 to December 31, 2019, and a park and a parking lot construction project (hereinafter “instant construction project”).

The construction of this case is a large-scale construction project that takes more than two years for the entire F, and the defendant bears the duty to safely manage ground water, rock water, sewage pipes, etc. so that it does not cause damage to neighboring houses.

However, while the defendant neglected this and neglected the construction of the instant case, the sewerage of the instant housing was flown up, and accordingly the instant housing was flooded.

In order to recover this, the plaintiff suffered damages of approximately KRW 50 million in total, including construction cost, cost of household goods, and consolation money, so that the plaintiff can seek to pay the above money to the defendant.

2. The Plaintiff’s assertion is insufficient to acknowledge only with the descriptions of evidence Nos. 1 through 3 (including paper numbers), and there is no other evidence to acknowledge it.

Therefore, the plaintiff's assertion is without merit.

3. The plaintiff's claim of this case is without merit.