Text
1. The defendant shall pay to the plaintiff KRW 31,376,437 and KRW 31,00,000 among them, from December 24, 2019 to the day of full payment.
Reasons
The Defendant: (a) determined on November 16, 2019 as the due date for repayment of KRW 20 million on October 15, 2019; (b) determined as the due date for repayment of KRW 20 million on October 17, 2019; (c) determined as the due date for repayment of KRW 12 million on October 28, 2019; and (d) agreed to pay at least 5% interest per annum on October 25, 2019 at the due date for repayment of KRW 1 million on November 5, 2019; (b) the Defendant appropriated the Plaintiff to the principal of the borrowed money as the principal on November 1, 2019; and (b) agreed to pay at least one million interest per annum to the Plaintiff during the due date for repayment of KRW 20,000,000 among the principal amount on November 19, 2019; and (b) concluded that there is no dispute between the Plaintiff and the entire parties to the loan.
According to the above facts of recognition, the defendant shall make an agreement to the plaintiff, which is calculated by the rate of 5% per annum from October 15, 2019 to November 19, 2019, on the remaining 31 million won of the principal of the borrowed amount, and the annual rate of 98,630 won of the borrowed amount, and 20 million won of the borrowed amount, calculated by the rate of 5% per annum from October 17, 2019 to November 1, 2019, on the annual rate of 43,835 won of the borrowed amount and 19 million won from November 2, 2019 to December 23, 2019, on the annual rate of 43,835 won of the borrowed amount, and 19 million won of the borrowed amount from November 23, 2019 to December 25, 2013, 2000 won of the borrowed amount and 205.
In addition, the Plaintiff separately sought payment of KRW 145,973 with interest of KRW 12% per annum from December 24, 2019 to January 29, 2020, which is the day following the delivery date of a copy of the instant complaint for the remainder of KRW 19 million from December 24, 2019, and KRW 231,123 with interest of KRW 12% per annum from December 24, 2019 to January 29, 2020, the day following the delivery date of a copy of the instant complaint for the remainder of KRW 31 million. However, the Plaintiff separately sought payment with interest of KRW 145,973 with interest calculated at 12% per annum from January 24, 2019 to January 29, 2020.