(영문) 수원지방법원 평택지원 2017.03.29 2016가합8253
부동산인도등
Text

1. The defendant

(a) deliver each real estate listed in Schedule 1 to 5;

(b) KRW 161,087,000; and

Reasons

1. Basic facts

A. The Defendant for the cudio facility project between the Defendant and B (hereinafter “B”) is a corporation B (hereinafter “B”).

(1) On October 16, 2012, the building listed in [Attachment 6] No. 6 (hereinafter “instant building”).

(2) On October 20, 2012, the payment for the interior studio installation works was awarded a contract for the 16.5 million won of the construction cost, respectively. (2) The Defendant received from B on November 5, 2012 the payment for the interior cudio installation works of the instant building for freezing and cooling and cooling storage facilities (including value added tax; hereinafter the same shall apply) 440 million won of the construction cost.

(hereinafter referred to as “each construction of this case”). B.

1) On January 15, 2013, the Defendant filed a lawsuit against B on January 15, 2013 against B seeking payment of KRW 400 million out of the above construction price against C, which is a joint and several surety for freezing/conditioning facilities, including KRW 88 million = 165 million in total, and KRW 440 million in total, and KRW 440 million in total, among the above construction price (the Daejeon District Court Decision 2013Gahap10043, Jan. 6, 2014), against the Defendant, B, and D except Daejeon (the Daejeon District Court Decision 2013Da10043, Jan. 6, 2014). The said decision became final and conclusive around that time as follows:

(hereinafter “instant compulsory conciliation”) 1. The Defendant:

(a) B and D shall be paid jointly and severally by January 20, 2014, by up to 440 million won, and if the payment date is due, by adding an annual interest rate of 20% to the unpaid amount from January 21, 2014 to the date of full payment;

B. B shall be paid up to February 20, 2014, by up to 36.1 million won, and where the above payment date is due, the unpaid amount shall be paid in addition to the delay damages calculated at the rate of 20% per annum from February 21, 2014 to the date of full payment.

2. B and D shall thereafter be filed against the future Defendant, which is installed and installed on the E-ground when the Defendant is Ansan-si;