(영문) 인천지방법원 2017.12.07 2016가합51145
물품대금
Text

1. All claims filed by the Plaintiff (Counterclaim Defendant) and the counterclaim claims by the Defendant (Counterclaim Plaintiff) are dismissed.

2. Of the costs of lawsuit.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

Basic Facts

The plaintiff is a person engaged in the manufacturing business of equipment with the trade name "D" located in Daegu-gu, and the defendant is a company with the purpose of manufacturing and repairing automation machinery.

On December 10, 2014, the Plaintiff entered into a contract for the manufacture of equipment between the Plaintiff and the Defendant (hereinafter “instant contract”) with the Defendant, and entered into a contract for the manufacture of GPC hydrotension TET machinery (hereinafter “instant contract”). The main contents of the said contract and written estimates in relation to the said contract are as follows.

The defendant (A) and D (D) shall sign and seal the contract and enter into an agreement to perform the contract in good faith.

1. Manufacturing and installing the EPC water pressure test equipment in the name of the Corporation;

2. Place of construction: E (State) Incheon engine plant.

3. Period of construction: December 11, 2014 to February 15, 2015;

4. Total amount of construction - Total amount of construction - 160,000,000 won - Additional dues - Additional dues - Additional dues - Additional dues - 1) Part part payments : 80,000,000 won (sale0 million won) - Part part payments 2 (30%) part payments after the end of December 14 : 4: 48,000 won (sale million won): 32,000,000 won after self-working and inspection: 30%) balance (20%) after completion of construction: 32,00,000 won (three million won): 16 (10:0,000 won for each contract completion date after completion of construction: 10% of the contract amount after completion of construction is completed; 20% of the contract amount shall be paid immediately after completion of construction after completion of construction: 10% of the contract amount after completion of construction after completion of construction: 10% of the contract.

2. "Completion inspection" shall complete a trial run after the manufacture of equipment and satisfy the supplemental cadastral matters.

In addition, producers' driving education and preservation team's remuneration education are provided once every time.