(영문) 서울고등법원 2013.11.08 2013나2005600
보험금
Text

1. The plaintiff's appeal is dismissed.

2. The costs of appeal shall be borne by the Plaintiff.

Purport of claim and appeal

The first instance court.

Reasons

1. Basic facts

A. 1) On November 21, 2007, the Ansan market changed the trade name A Co., Ltd. (B) to B, a corporation after which the first implementation plan was approved and the guarantee insurance contract was concluded;

hereinafter referred to as “foreign company”

The former National Land Planning and Utilization Act (amended by Act No. 8852 of Feb. 29, 2008; hereinafter referred to as the “former National Land Planning Act”) shall apply to the members of Ansan-si C.

2) The project undertaken to create a golf course, which is an urban planning facility, (hereinafter “instant project”).

As to the project, the project implementer approved the non-party company as the non-party company, the project period from September 20, 2007 to December 31, 2009 (hereinafter “instant implementation plan”).

(2) On September 21, 2007, after consultation with the Gyeonggi-do Governor on the conversion of a mountainous district on the instant project with the Governor of the Gyeonggi-do, prior to the authorization of the instant implementation plan, the implementation plan was approved, and the following vice officers were added with regard to the conversion of a mountainous district (hereinafter “the vice officers of the instant case”).

4. Gyeonggi-do forest greenbelts and farmland conversion consultation - This consultation shall not take effect until urban planning facilities are authorized pursuant to the provisions of relevant Acts and subordinate statutes, such as urban planning facilities, etc. pursuant to the provisions of Article 16 of the Management of Mountainous Districts Act, and if the rejection or revocation of administrative dispositions necessary

(b) Where an implementation plan is authorized pursuant to an urban planning facility, he/she shall, without delay, notify the Do (forest department) and the Ansan City (forest department), and where he/she intends to modify the consulted matters, re-consultation;

(b)Authorization of an implementation plan of an urban planning facility shall:

4. Restoration of an exclusive mountainous district shall be restored by the non-party company, and an order shall be issued to take measures necessary to prevent disasters or recover from disasters even during the period of conversion, if such order is issued, such order shall be complied with.

(b) 5.