(영문) 서울중앙지방법원 2020.01.15 2019나27283
용역비
Text

1. Of the part regarding the principal claim in the judgment of the court of first instance, the part concerning the Defendant-Counterclaim Plaintiff’s claim against the Plaintiff (Counterclaim Defendant) is 19,189.

Reasons

A principal lawsuit and a counterclaim shall also be deemed to have been filed.

1. Facts of recognition;

A. On March 4, 2016, the Plaintiff: (a) received a service agreement (hereinafter referred to as “instant service agreement”); (b) that received system planning, design, and tableing from March 7, 2016 to October 6, 2016 (including value-added tax, KRW 55,440,00, intermediate payment (30%) from the Defendant, KRW 184,80,000 (including value-added tax, KRW 30%) from the Defendant, KRW 55,440,00, and the balance (40%) (hereinafter referred to as “instant service agreement”); and (c) concluded the service agreement with the Plaintiff to provide the service that the Plaintiff performed.

B. The project of this case is divided into the first step and the second step, the second step, the development stage, the third step, and the fourth step, and the fourth step. The plaintiff, among which, in manufacturing the planning and development stage of the design and development stage, shall arrange the idea of how the development process can be exposed to the users in any form and form. The plaintiff, from the perspective of designing the design planned idea, shall practice the text and image, which are viewed as the user as the program, etc., and shall connect the design of the crying to the development program, which is linked to the development program developed by the defendant and shall be operated by the defendant, and the defendant shall perform the design, process design, DB design, program design, program design, etc., the development system design, development plan, development guidelines preparation, etc., and shall be designated as a general manager of the project of this case and all other work of this case including the management manager of the project of this case.