(영문) 창원지방법원 진주지원 2016.03.31 2015고단1098
배임
Text

A defendant shall be punished by imprisonment for six months.

However, the execution of the above sentence shall be suspended for a period of two years from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

On December 3, 2010, the Defendant: (a) obtained a loan of KRW 700 million from the Victim Small and Medium Business Corporation located in Jinju-si; and (b) established a collateral security at KRW 840 million with respect to the said real estate as collateral for the said debt; (c) on February 22, 2011, with respect to the collateral security established as above, the Defendant created a change into a factory and a collateral security under the Mining Foundation Mortgage Act by providing all 17-type machinery equipment, a factory machine, as additional security, as well as 17-type type, with regard to the collateral security established around February 22, 2011. As such, the Defendant was the Defendant, who was a debt manager prior to the repayment of the above loan, and was required to manage the said comprehensive collateral security property as a collateral for the person who created the collateral security interest.

Nevertheless, the defendant violated the above duties and from August 2013 to February 2014, the above company D, and factory productionist, while changing the facilities of the above company, and the above company, the defendant acquired 1 type (the appraised appraised value of KRW 98,670,00), 1 type (the appraised value of KRW 18,000,000), 50 tons of 50 tons of 10 tons of 10 tons of 10,000 of 10,000 of 10 tons of 10,000, 1 type (the appraised value of KRW 23,16,000), 1 type (the appraised value of KRW 23,16,00), 0.5 tons of 1 type (the appraised value of KRW 9,408,300, 300, 400, 400, 50, 50, 40, 50, 50

Summary of Evidence

1. Statement by the defendant in court;

1. Statement made by the police for E;

1. Loan agreement (as of December 3, 2010), 70 million won - 700 million won, loan agreement (as of August 12, 2013), - KRW 500 million, loan music agreement (as of November 25, 2013), KRW 80 million, loan agreement (as of November 25, 2013), KRW 120 million, loan agreement (as of November 25, 2013), KRW 268 million, loan agreement (as of November 25, 2013), and collateral security agreement (as of December 3, 2010)