Text
1. The Defendants shall jointly and severally pay to the Plaintiff KRW 97,984,00 and the interest rate thereon from November 22, 2017 to the date of full payment.
Reasons
1. Determination on the cause of the claim
A. Comprehensively taking account of each of the statements in subparagraphs A and 5 as a whole, the Plaintiff traded goods with the Defendant Company, and as of April 18, 2015, the Plaintiff’s failure to pay the goods amounting to KRW 98,684,000 to the Plaintiff Company as of April 18, 2015. As the Plaintiff’s representative director D demanded reimbursement of the Defendant Company around July 14, 2016, the Defendant Company’s representative director C as the obligee and the obligor, and the Defendant Company’s representative director as of April 8, 2015 as of April 98,68,684,00 and promised to fully pay the said obligation.
B. According to the above facts, Defendant C is jointly and severally liable for the Defendant Company’s obligations. As such, the Defendants are jointly and severally liable to the Plaintiff to pay the remainder of KRW 700,000 to the Plaintiff out of the balance of the price of the goods in question, and the damages for delay calculated at the rate of 15% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from November 22, 2017 to the date of full payment, upon the Plaintiff’s request, as the remainder of KRW 97,984,00 to the Plaintiff out of the balance of the goods in question and after the due date.
2. Therefore, the plaintiff's claim of this case against the defendants is justified, and it is so decided as per Disposition.