Text
1. The Plaintiff, Defendant B, Defendant C, Defendant C, KRW 21,817,532, and each of them, from August 8, 2015 to August 25, 2017.
Reasons
1. Basic facts
A. Defendant B is an owner of the area of 2,895 square meters in Yangyang-gun, Gyeonggi-do. Defendant C is an owner of the area of 895 square meters in the area of the farm land E, while Defendant C is an owner of the area of 502 square meters in the area of the F farm land.
B. On April 17, 2015, Defendant B entered into a contract for civil engineering works on each of the above lands with the Plaintiff as follows.
The date of commencement: The construction cost on August 2015: 110,000,000 won (including value-added tax): 15% 16,000,000 won intermediate payment (after commencement of construction): 40% remainder ( simultaneously with completion of construction) of 44,00,000 won: 45% 50,000,000 won in principle, and may be revised under an agreement, in cases of changes, under agreement.
(Provided, That in the event of a change or additional construction, the drawings and amount shall be separately calculated, and the construction shall be performed after obtaining a notice from Defendant B. In principle, all the problems arising after the contract shall be all the responsibility of the Plaintiff.
After the lapse of 3.5 months from the date of remitting down payment, 1,000,000 won per day shall be paid as compensation for delay.
The defect repair period shall be five years.
C. On January 13, 2015, Defendant C entered into a contract for the following summary (hereinafter referred to as “instant contract”) with the Plaintiff regarding the civil works on each of the above lands (hereinafter referred to as “instant construction works” together with the aforementioned construction works) (hereinafter referred to as “instant contract”).
Construction cost: 67,00,000 won (including value-added tax) : 30% 20,000,000 won (after commencement of the construction: 30% 20,000,000 won (after commencement of the construction): 40% 27,000,000 won (other conditions are the same as the above)
D. From April 21, 2015, the Plaintiff performed the instant construction from around April 21, 2015. Defendant B paid the Plaintiff KRW 60,000,000 as an advance payment, and KRW 44,000,000 as an intermediate payment on April 21, 2015, and Defendant C paid the Plaintiff KRW 60,00,000,000.