Text
1. The defendant's appeal is dismissed.
2. The costs of appeal shall be borne by the Defendant.
Purport of claim and appeal
1...
Reasons
1. Determination on the cause of the claim
A. 1) On September 10, 201, A had the total construction cost of KRW 147,00,00 (excluding value-added tax) between the Defendant, KRW 147,00,00 among new construction works of Cridges, KRW 80,00 (excluding value-added tax) and completed the construction work upon being awarded a subcontract on September 15, 201, KRW 80,00, KRW 400, KRW 700, KRW 00, KRW 700, KRW 700, KRW 700, KRW 800, KRW 700, KRW 700, KRW 80, KRW 700, KRW 700, KRW 700, KRW 800, KRW 700, KRW 700, KRW 700, KRW 700, KRW 700, KRW 700, KRW 700, KRW 700, KRW 700,000.
(2) The Defendant paid KRW 4,700,000 to H, a business partner of A, and paid KRW 33,641,409 (= KRW 60,341,409 - KRW 22,000,000) for the settlement of this case. A additionally received part of the settlement of this case from the Defendant, and paid KRW 9,70,000 (hereinafter “the remainder settlement of this case”) for the settlement of this case.
(4) On November 30, 2014, A transferred the remaining claims to the Plaintiff, notified the Defendant of the purport of the assignment of claims on the same day, and reached the Defendant around that time.
[Ground of recognition] Unsatisfy, Gap evidence 1 to 9.