(영문) 대전지방법원천안지원 2017.05.26 2016가합102293
공사대금
Text

1. The plaintiff

A. Defendant White Construction Co., Ltd.: KRW 399,727,273 and this shall be from October 21, 2016.

Reasons

1. Basic facts

A. 1) The Plaintiff is a person running a construction business, such as construction and civil engineering work, with the trade name of “C”. 2) Defendant B is a person operating a mutually named business entity, and Defendant B entered into the instant construction contract with the Defendant Company as to “D” and “F projects (hereinafter “instant projects”) on the ground (hereinafter “the instant project”). Defendant 00,000,000,000,000 won and the remainder of the construction work price under the instant construction contract (hereinafter “the instant construction contract”). The Plaintiff is a contractor who entered into the said new construction contract with the Defendant Company as the contractor of the instant project. (B) On March 5, 2016, the date of completion of the instant new construction contract between the Defendant Company and the Plaintiff Company as the contractor of the instant project, and the date of completion of the construction contract between the Plaintiff and the date of completion of the construction work under the instant construction contract (including container packaging and landscaping) and the date of completion of the construction contract (hereinafter “the instant construction contract”).

" ........"

The above agreement is referred to as the "agreement in this case".

(3) On March 8, 2016, the Plaintiff received the down payment of KRW 30 million out of the construction price under the instant construction contract.

4 The Plaintiff agreed to perform an additional construction project equivalent to KRW 7 million for the construction cost under the instant construction contract between the Defendant Company and the Defendant Company. After that, the Plaintiff completed both the construction project and the said additional construction project under the instant construction contract.

C. Defendant B, the implementer of the instant project, such as the agreement on the composition of the subcontractor’s claim group and the payment of the construction cost, is the financial shortage of the Defendant Company.