logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대전지방법원천안지원 2014.07.01 2013가합716
공사대금
Text

1. The Defendant’s KRW 124,602,711 as well as the Plaintiff’s annual rate of 6% from March 5, 2013 to July 1, 2014, and the following.

Reasons

The plaintiff is a company whose objective is construction work execution, etc., and the defendant is an engineering work company, etc.

The Plaintiff entered into the instant construction contract with the Defendant during August 201, and entered into a subcontract (No. 6, hereinafter “instant construction contract”) with the Defendant as follows.

Article 1 (Integrated Construction Name) Construction Works for Crossing Private Sewage Treatment Facilities - Contract Price: 200,000,000 won for fixed-term supply of machinery and pipes for private sewage treatment facilities: 200,000,000 won for fixed-term supply: 20,000,000 won for fixed-term supply: Construction Work Place (2) for Gangwon-do Crossing-gun Crossing-gun Crossing-gun (3) Construction Work Period: Article 3 (Contract Details) attached to the payment terms of the Korea Highway Corporation from June 1, 201 to October 30, 201, Article 4 (Contract Details) attached to Article 5 (Contract Details) (1) : 10% of the contract price for advance payment: 100,000 won for advance payment: 20,000 won for the place of construction work: 30% of the final defect at the construction site designated by the Defendant (25% of the contract price for advance payment).

§ 7 (1) The goods supplied shall be the goods of the same regulation, performance, and material as the original contract terms and conditions, and the goods that have failed to be inspected shall immediately be substituted by the ordering office.

In this case, the plaintiff may not request an extension of the contract term on its ground.

(2) Before the delivery, installation and trial completion of the goods referred to in paragraph (1) above, the loss, damage, etc. of the said goods shall be borne by the plaintiff in full.

Article 8 (Compensation for Delay) When the Plaintiff did not supply or install all or part of the goods by the delivery deadline designated by the Defendant, the Plaintiff shall deduct the amount equivalent to 1/1,000 of the contract price per day of delay days from the delivery penalty for delay.

However, natural disasters or the plaintiff.

arrow