(영문) 춘천지방법원강릉지원 2015.01.15 2014가합100187
손해배상(기)
Text

1. All of the plaintiff's claims are dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On July 31, 2012, the Plaintiff: (a) received from the Future Comprehensive Construction Co., Ltd. (hereinafter “Smi Construction”); (b) the H New Construction Work of Gilwon in G (hereinafter “instant Construction”) on April 30, 2013; and (c) received KRW 13.25 billion of the contract amount at KRW 13.25 billion.

B. On November 20, 2012, the Plaintiff entered into a contract with I Co., Ltd. (hereinafter “I”) to subcontract the portion of civil engineering works among the instant construction works.

C. Defendant A, while operating J from December 2012 to April 30, 2013, performed the work of dump trucking the sand crushed from the excavated machine with respect to the instant construction project. However, Defendant A did not receive construction cost of KRW 32,202,50 regarding the work from March 1, 2013 to April 30, 2013.

Defendant B, while operating K, performed the work of putting dump trucks installed with respect to the instant construction project from December 12, 2012 to April 30, 2013. However, Defendant B did not receive construction payment of KRW 19,987,00 for the work from March 11, 2013 to April 30, 2013.

E. Defendant C, while operating L, performed the work of inserting two dump trucks with respect to the instant construction project from November 30, 2012 to February 28, 2013, and transporting dump trucks to reclaimed land. However, Defendant C did not receive construction cost of KRW 6,235,625 on February 2013.

F. In the course of managing M, Defendant D was engaged in blasting steel rocks, etc. underground in the instant construction site with powders, etc. from January 2013 to April 2013, but did not receive construction cost of KRW 90,845,00 for March and April 2013.

G. In relation to the instant construction project from December 2, 2012 to April 2013, Defendant Dong-dong Development Co., Ltd.: (a) carried 8 tons of dump trucks and 15 tons of dump trucks to transport private land to reclaimed land; (b) however, the construction cost of KRW 170,568,40 on the work after February 2013 is paid.